8.3.4.1-8.3.4.3IATF 16949 ONLYIATF 16949:2016

D&D monitoring, validation suppl., prototypes (IATF only)

Plain-language summary

Measure design projects at defined stages and report to management (and customer if required); validate per customer requirements including any industry/government timing; run a prototype programme with control plan when the customer requires one.

What the clause is really asking

Three additions: project measurements (quality/cost/timing) monitored at defined stages and reported; validation aligned to customer programme timing and any regulatory schedules; prototype programme with its own control plan, using production-intent suppliers/tooling/processes wherever possible, with subcontracted services controlled.

What auditors look for

Auditors ask for project status reporting evidence (open issues, timing vs plan), validation timing against the customer milestone plan, and the prototype control plan with conformity records for prototype parts.

Typical evidence

Project dashboards/status reports; validation schedules tied to customer milestones; prototype control plans and results.

How to comply — recommendations

Run a one-page project scorecard (timing, open issues, risks) per active project, reviewed monthly. Write the prototype control plan as a draft of the production one — same document maturing, less work.

Common nonconformities

No measurable project tracking; validation slipping past customer milestones unflagged; prototypes built with no control plan or records.

Related clauses

Builds on ISO 9001 8.3.4